Copying Entities from one Layer to another Layer

Tips and tricks you want to share with other users. Tutorials, user submitted documentation, etc.

Moderator: andrew

Post Reply
User avatar
andrew
Site Admin
Posts: 9019
Joined: Fri Mar 30, 2007 6:07 am

Copying Entities from one Layer to another Layer

Post by andrew » Tue May 26, 2015 1:49 pm

- Select the entities you want to copy. So select everything on the current layer choose Select > Select Layer
- Edit > Copy (or Copy with Reference)
- Edit > Paste
- Tick the box "To current Layer" in the top toolbar while pasting:
Screen Shot 2015-05-26 at 14.42.42.png
Screen Shot 2015-05-26 at 14.42.42.png (30.39 KiB) Viewed 15212 times